Hunter Valley Mine Site Project

waterTreatment-HunterValley

Below are details of the work Bushmans Tanks have completed in the water treatment field.

State NSW

 

Background

This client operates a mine and has an ambitious project to capture water. 

Project concept

The client needed to process water from the mine site, so the tanks had to serve a large demand application, predominately for dust suppression on haul roads.

With this solution the water could be pumped into tankers and sprayed onto heavy traffic areas. The biggest challenge was designing and fabricating the tanks according to the customer’s construction drawings. 

Products manufactured 

10 x T10500IND 46,000 L  SG 1.2 with factory fitted DN250 & DN300 stub flange

Resources

Design 

Engineering 

Manufacture 

Delivery 

Solution

Considering the challenge of fabricating these tanks as per the customer’s construction drawings, Bushmans engineers and tank specialists were able to provide a turn-key solution for the large volumes of water storage required in this application.

Bushmans not only mastered the tank manufacturing but also installed the tank flanges and fittings following the clients’ guidelines.

This allowed all the pipe work to be prefabricated prior to installation. Once the tanks were delivered to site, the connection and commissioning was quickly completed providing a fast, robust system that will satisfy the rigorous demands of most mining applications.  

View more projects